AB75-SSA1-CA1,68,5 5336. Page 700, line 1: after that line insert:
AB75-SSA1-CA1,68,6 6" Section 1480b. 66.0903 (1) (im) of the statutes is created to read:
AB75-SSA1-CA1,68,117 66.0903 (1) (im) "Supply and installation contract" means a contract under
8which the material is installed by the supplier, the material is installed by means of
9simple fasteners or connectors such as screws or nuts and bolts and no other work
10is performed on the site of the project of public works, and the total labor cost to
11install the material does not exceed 20 percent of the total cost of the contract.".
AB75-SSA1-CA1,68,13 12337. Page 700, line 4: delete "remodeled, repaired, or demolished" and
13substitute "repaired, remodeled, demolished, or improved".
AB75-SSA1-CA1,68,15 14338. Page 700, line 6: delete "or bridge construction" and substitute "bridge,
15building, or other infrastructure".
AB75-SSA1-CA1,68,16 16339. Page 700, line 7: delete that line and substitute:
AB75-SSA1-CA1,68,17 17"(b) A project erected, constructed, repaired, remodeled,".
AB75-SSA1-CA1,68,18 18340. Page 700, line 8: after "demolished" insert ", or improved".
AB75-SSA1-CA1,68,20 19341. Page 700, line 9: delete "66.0301 (2) or 83.035" and substitute "66.0301
20(2), 83.03, 83.035, or 86.31 (2) (b)".
AB75-SSA1-CA1,68,21 21342. Page 700, line 11: delete that line and substitute:
AB75-SSA1-CA1,68,22 22"(c) A project in which the completed facility is leased,".
AB75-SSA1-CA1,69,2
1343. Page 700, line 14: delete that line and substitute "erection, construction,
2repair, remodeling, demolition, or improvement of the facility.".
AB75-SSA1-CA1,69,3 3344. Page 700, line 15: after "street," insert "bridge,".
AB75-SSA1-CA1,69,6 4345. Page 700, line 16: delete that line and substitute "road, street, bridge,
5sanitary sewer, or water main is acquired by, or dedicated to, a local governmental
6unit, including".
AB75-SSA1-CA1,69,8 7346. Page 700, line 17: delete "(2) for ownership" and substitute "(2), for
8ownership or maintenance".
AB75-SSA1-CA1,69,10 9347. Page 700, line 18: delete the material beginning with that line and
10ending with page 701, line 6 and substitute:
AB75-SSA1-CA1,69,11 11" Section 1480e. 66.0903 (3) (am) of the statutes is amended to read:
AB75-SSA1-CA1,69,2412 66.0903 (3) (am) A local governmental unit, before making a contract by direct
13negotiation
or soliciting bids on a contract, for the erection, construction, remodeling,
14repairing or, demolition, or improvement of any project of public works, including a
15highway, street or bridge construction project,
shall apply to the department to
16determine the prevailing wage rate for each trade or occupation required in the work
17contemplated under contemplation in the area in which the work is to be done. The
18department shall conduct investigations and hold public hearings as necessary to
19define the trades or occupations that are commonly employed on projects of public
20works
that are subject to this section and to inform itself as to the prevailing wage
21rates in all areas of the state for those trades or occupations, in order to determine
22the prevailing wage rate for each trade or occupation. The department shall issue
23its determination within 30 days after receiving the request and shall file the
24determination with the requesting local governmental unit.
AB75-SSA1-CA1, s. 1480g
1Section 1480g. 66.0903 (3) (ar) of the statutes is amended to read:
AB75-SSA1-CA1,70,82 66.0903 (3) (ar) The department shall, by January 1 of each year, compile the
3prevailing wage rates for each trade or occupation in each area. The compilation
4shall, in addition to the current prevailing wage rates, include future prevailing
5wage rates when those prevailing wage rates can be determined for any trade or
6occupation in any area and shall specify the effective date of those future prevailing
7wage rates. If a construction project of public works extends into more than one area
8there shall be but one standard of prevailing wage rates for the entire project.".
AB75-SSA1-CA1,70,9 9348. Page 701, line 13: after that line insert:
AB75-SSA1-CA1,70,10 10" Section 1481f. 66.0903 (3) (br) of the statutes is amended to read:
AB75-SSA1-CA1,70,2411 66.0903 (3) (br) In addition to the recalculation under par. (bm), the local
12governmental unit that requested the determination under this subsection may
13request a review of any portion of a determination within 30 days after the date of
14issuance of the determination if the local governmental unit submits evidence with
15the request showing that the prevailing wage rate for any given trade or occupation
16included in the determination does not represent the prevailing wage rate for that
17trade or occupation in the city, village, or town in which the proposed project of public
18works
is located. That evidence shall include wage rate information for the contested
19trade or occupation on at least 3 similar projects located in the city, village, or town
20where the proposed project of public works is located and on which some work has
21been performed during the current survey period and which were considered by the
22department in issuing its most recent compilation under par. (ar). The department
23shall affirm or modify the determination within 15 days after the date on which the
24department receives the request for review.".
AB75-SSA1-CA1,70,25
1349. Page 701, line 18: after "project" insert "of public works".
AB75-SSA1-CA1,71,2 2350. Page 702, line 8: after that line insert:
AB75-SSA1-CA1,71,3 3" Section 1481j. 66.0903 (4) (a) 1. of the statutes is amended to read:
AB75-SSA1-CA1,71,54 66.0903 (4) (a) 1. All laborers, workers, mechanics , and truck drivers employed
5on the site of a project of public works that is subject to this section.
AB75-SSA1-CA1, s. 1481L 6Section 1481L. 66.0903 (4) (a) 2. of the statutes is amended to read:
AB75-SSA1-CA1,71,127 66.0903 (4) (a) 2. All laborers, workers, mechanics , and truck drivers employed
8in the manufacturing or furnishing of materials, articles, supplies , or equipment on
9the site of a project of public works that is subject to this section or from a facility
10dedicated exclusively, or nearly so, to a project of public works that is subject to this
11section by a contractor, subcontractor, agent, or other person performing any work
12on the site of the project.
AB75-SSA1-CA1, s. 1481m 13Section 1481m. 66.0903 (4) (b) 1. of the statutes is amended to read:
AB75-SSA1-CA1,71,2014 66.0903 (4) (b) 1. The laborer, worker, mechanic, or truck driver is employed
15to go to the source of mineral aggregate such as sand, gravel, or stone that is to be
16immediately incorporated into the work, and not stockpiled or further transported
17by truck, pick up that mineral aggregate, and deliver that mineral aggregate to the
18site of a project of public works that is subject to this section by depositing the
19material substantially in place, directly or through spreaders from the transporting
20vehicle.
AB75-SSA1-CA1, s. 1481n 21Section 1481n. 66.0903 (4) (b) 2. of the statutes is amended to read:
AB75-SSA1-CA1,72,222 66.0903 (4) (b) 2. The laborer, worker, mechanic, or truck driver is employed
23to go to the site of a project of public works that is subject to this section, pick up

1excavated material or spoil from the site of the project, and transport that excavated
2material or spoil away from the site of the project.".
AB75-SSA1-CA1,72,3 3351. Page 702, line 9: delete lines 9 to 14.
AB75-SSA1-CA1,72,4 4352. Page 703, line 7: delete lines 7 and 8 and substitute:
AB75-SSA1-CA1,72,5 5" Section 1482j. 66.0903 (5) (c) of the statutes is created to read:
AB75-SSA1-CA1,72,76 66.0903 (5) (c) Minor service or maintenance work, warranty work, or work
7under a supply and installation contract.
AB75-SSA1-CA1, s. 1482L 8Section 1482L. 66.0903 (8) of the statutes is amended to read:
AB75-SSA1-CA1,72,159 66.0903 (8) Posting. For the information of the employees working on the
10project of public works, the prevailing wage rates determined by the department or
11exempted local governmental unit, the prevailing hours of labor, and the provisions
12of subs. (10) (a) and (11) (a) shall be kept posted by the local governmental unit in at
13least one conspicuous and easily accessible place on the site of the project or, if there
14is no common site on the project, at the place normally used by the local
15governmental unit to post public notices.
AB75-SSA1-CA1, s. 1482n 16Section 1482n. 66.0903 (9) (b) of the statutes is amended to read:
AB75-SSA1-CA1,72,2217 66.0903 (9) (b) Upon completion of a project of public works and before
18receiving final payment for his or her work on the project, each agent or
19subcontractor shall furnish the contractor with an affidavit stating that the agent
20or subcontractor has complied fully with the requirements of this section. A
21contractor may not authorize final payment until the affidavit is filed in proper form
22and order.
AB75-SSA1-CA1, s. 1482p 23Section 1482p. 66.0903 (9) (c) of the statutes is amended to read:
AB75-SSA1-CA1,73,15
166.0903 (9) (c) Upon completion of a project of public works and before receiving
2final payment for his or her work on the project, each contractor shall file with the
3local governmental unit authorizing the work an affidavit stating that the contractor
4has complied fully with the requirements of this section and that the contractor has
5received an affidavit under par. (b) from each of the contractor's agents and
6subcontractors. A local governmental unit may not authorize a final payment until
7the affidavit is filed in proper form and order. If a local governmental unit authorizes
8a final payment before an affidavit is filed in proper form and order or if the
9department determines, based on the greater weight of the credible evidence, that
10any person performing the work specified in sub. (4) has been or may have been paid
11less than the prevailing wage rate or less than 1.5 times the hourly basic rate of pay
12for all hours worked in excess of the prevailing hours of labor and requests that the
13local governmental unit withhold all or part of the final payment, but the local
14governmental unit fails to do so, the local governmental unit is liable for all back
15wages payable up to the amount of the final payment.
AB75-SSA1-CA1, s. 1483d 16Section 1483d. 66.0903 (10) (a) of the statutes is amended to read:
AB75-SSA1-CA1,73,2217 66.0903 (10) (a) Each contractor, subcontractor, or contractor's or
18subcontractor's agent performing work on a project of public works that is subject to
19this section shall keep full and accurate records clearly indicating the name and
20trade or occupation of every person performing the work described in sub. (4) and an
21accurate record of the number of hours worked by each of those persons and the
22actual wages paid for the hours worked.".
AB75-SSA1-CA1,74,4 23353. Page 703, line 16: delete lines 16 and 17 and substitute "apply to a
24contractor, subcontractor, or agent if all persons employed by the contractor,

1subcontractor, or agent who are performing the work described in sub. (4) are covered
2under a collective bargaining agreement and the wage rates for those persons under
3the collective bargaining agreement are not less than the prevailing wage rate. In
4that case, the contractor,".
AB75-SSA1-CA1,74,7 5354. Page 703, line 19: delete "the collective bargaining agreement" and
6substitute "all collective bargaining agreements that are pertinent to the project of
7public works".
AB75-SSA1-CA1,74,8 8355. Page 704, line 4: after that line insert:
AB75-SSA1-CA1,74,9 9" Section 1483h. 66.0903 (10) (b) of the statutes is amended to read:
AB75-SSA1-CA1,74,1810 66.0903 (10) (b) The department or the contracting local governmental unit
11may demand and examine, and every contractor, subcontractor, and contractor's or
12subcontractor's agent shall keep, and furnish upon request by the department or
13local governmental unit, copies of payrolls and other records and information
14relating to the wages paid to persons performing the work described in sub. (4) for
15work to which this section applies. The department may inspect records in the
16manner provided in ch. 103. Every contractor, subcontractor, or agent performing
17work on a project of public works that is subject to this section is subject to the
18requirements of ch. 103 relating to the examination of records.".
AB75-SSA1-CA1,74,19 19356. Page 704, line 8: after "project" insert "of public works".
AB75-SSA1-CA1,74,20 20357. Page 704, line 24: after that line insert:
AB75-SSA1-CA1,74,22 21" Section 1484f. 66.0903 (11) (a) of the statutes is renumbered 66.0903 (11) (a)
221. and amended to read:
AB75-SSA1-CA1,75,623 66.0903 (11) (a) 1. Any contractor, subcontractor, or contractor's or
24subcontractor's agent who fails to pay the prevailing wage rate determined by the

1department under sub. (3) or who pays less than 1.5 times the hourly basic rate of
2pay for all hours worked in excess of the prevailing hours of labor is liable to any
3affected employee in the amount of his or her unpaid wages or his or her unpaid
4overtime compensation and in an additional equal amount as liquidated damages.
5An action to recover the liability may be maintained in any court of competent
6jurisdiction by any
as provided under subd. 2., 3., or 4., whichever is applicable.
AB75-SSA1-CA1,75,19 73. In addition to or in lieu of recovering the liability specified in subd. 1. as
8provided in subd. 2., any
employee for and in behalf of that employee and other
9employees similarly situated. may commence an action to recover that liability in
10any court of competent jurisdiction. In an action that is commenced before the end
11of any period specified by the department under subd. 2., if the court finds that a
12contractor, subcontractor, or contractor's or subcontractor's agent has failed to pay
13the prevailing wage rate determined by the department under sub. (3) or has paid
14less than 1.5 times the hourly basic rate of pay for all hours worked in excess of the
15prevailing hours of labor, the court shall order the contractor, subcontractor, or agent
16to pay to any affected employee the amount of his or her unpaid wages or his or her
17unpaid overtime compensation and an additional amount equal to 100 percent of the
18amount of those unpaid wages or that unpaid overtime compensation as liquidated
19damages.
AB75-SSA1-CA1,75,24 205. No employee may be a party plaintiff to the an action under subd. 3. or 4.
21unless the employee consents in writing to become a party and the consent is filed
22in the court in which the action is brought. Notwithstanding s. 814.04 (1), the court
23shall, in addition to any judgment awarded to the plaintiff, allow reasonable attorney
24fees and costs to be paid by the defendant.
AB75-SSA1-CA1, s. 1485g 25Section 1485g. 66.0903 (11) (a) 2. of the statutes is created to read:
AB75-SSA1-CA1,76,9
166.0903 (11) (a) 2. If the department determines upon inspection under sub.
2(10) (b) or (c) that a contractor, subcontractor, or contractor's or subcontractor's agent
3has failed to pay the prevailing wage rate determined by the department under sub.
4(3) or has paid less than 1.5 times the hourly basic rate of pay for all hours worked
5in excess of the prevailing hours of labor, the department shall order the contractor
6to pay to any affected employee the amount of his or her unpaid wages or his or her
7unpaid overtime compensation and an additional amount equal to 100 percent of the
8amount of those unpaid wages or that unpaid overtime compensation as liquidated
9damages within a period specified by the department in the order.
AB75-SSA1-CA1, s. 1485g 10Section 1485g. 66.0903 (11) (a) 4. of the statutes is created to read:
AB75-SSA1-CA1,76,2011 66.0903 (11) (a) 4. In an action that is commenced after the end of any period
12specified by the department under subd. 2., if the court finds that a contractor,
13subcontractor, or contractor's or subcontractor's agent has failed to pay the
14prevailing wage rate determined by the department under sub. (3) or has paid less
15than 1.5 times the hourly basic rate of pay for all hours worked in excess of the
16prevailing hours of labor, the court shall order the contractor, subcontractor, or agent
17to pay to any affected employee the amount of his or her unpaid wages or his or her
18unpaid overtime compensation and an additional amount equal to 200 percent of the
19amount of those unpaid wages or that unpaid overtime compensation as liquidated
20damages.".
AB75-SSA1-CA1,76,21 21358. Page 704, line 24: after that line insert:
AB75-SSA1-CA1,76,22 22" Section 1484t. 66.0903 (11) (b) 2. of the statutes is amended to read:
AB75-SSA1-CA1,77,723 66.0903 (11) (b) 2. Whoever induces any person who seeks to be or is employed
24on any project of public works that is subject to this section to give up, waive, or

1return any part of the wages to which the person is entitled under the contract
2governing the project, or who reduces the hourly basic rate of pay normally paid to
3a person for work on a project that is not subject to this section during a week in which
4the person works both on a project of public works that is subject to this section and
5on a project that is not subject to this section, by threat not to employ, by threat of
6dismissal from employment, or by any other means is guilty of an offense under s.
7946.15 (1).
AB75-SSA1-CA1, s. 1484v 8Section 1484v. 66.0903 (11) (b) 3. of the statutes is amended to read:
AB75-SSA1-CA1,77,189 66.0903 (11) (b) 3. Any person employed on a project of public works that is
10subject to this section who knowingly permits a contractor, subcontractor, or
11contractor's or subcontractor's agent to pay him or her less than the prevailing wage
12rate set forth in the contract governing the project, who gives up, waives, or returns
13any part of the compensation to which he or she is entitled under the contract, or who
14gives up, waives, or returns any part of the compensation to which he or she is
15normally entitled for work on a project that is not subject to this section during a
16week in which the person works both on a project of public works that is subject to
17this section and on a project that is not subject to this section, is guilty of an offense
18under s. 946.15 (2).".
AB75-SSA1-CA1,77,19 19359. Page 705, line 2: after "project" insert "of public works".
AB75-SSA1-CA1,77,20 20360. Page 705, line 8: after "project" insert "of public works".
AB75-SSA1-CA1,77,21 21361. Page 705, line 13: after that line insert:
AB75-SSA1-CA1,77,22 22" Section 1486f. 66.0903 (12) (d) of the statutes is amended to read:
AB75-SSA1-CA1,78,823 66.0903 (12) (d) Any person submitting a bid or negotiating a contract on a
24project of public works that is subject to this section shall, on the date the person

1submits the bid or negotiates the contract, identify any construction business in
2which the person, or a shareholder, officer or partner of the person, if the person is
3a business, owns, or has owned at least a 25% interest on the date the person submits
4the bid or negotiates the contract or at any other time within 3 years preceding the
5date the person submits the bid or negotiates the contract, if the business has been
6found to have failed to pay the prevailing wage rate determined under sub. (3) or to
7have paid less than 1.5 times the hourly basic rate of pay for all hours worked in
8excess of the prevailing hours of labor.".
AB75-SSA1-CA1,78,9 9362. Page 706, line 2: after that line insert:
AB75-SSA1-CA1,78,11 10"(am) "Bona fide economic benefit" has the meaning given in s. 103.49 (1)
11(am).".
AB75-SSA1-CA1,78,12 12363. Page 706, line 4: delete lines 4 to 19 and substitute:
AB75-SSA1-CA1,78,20 13"(c) "Direct financial assistance" means moneys, in the form of a grant or other
14agreement or included as part of a contract, cooperative agreement, or any other
15arrangement, including a redevelopment agreement under s. 66.1333 (5), economic
16development agreement, contract under s. 66.1105 (3), or assistance provided under
17s. 66.1109, that a local governmental unit directly provides or otherwise directly
18makes available to assist in the erection, construction, repair, remodeling,
19demolition, or improvement of a private facility. "Direct financial assistance" does
20not include any of the following:
AB75-SSA1-CA1,78,2421 1. A public works contract, a supply procurement contract, a contract of
22insurance or guaranty, a collective bargaining agreement, or any other contract
23under which moneys are not directly provided or otherwise directly made available
24for that assistance.
AB75-SSA1-CA1,79,8
12. Any moneys allocated by the city of Milwaukee for the purchase of public
2access easements that are located entirely in the Milwaukee Riverwalk Site Plan
3Review Overlay District established by the city of Milwaukee, as amended to June
41, 2009, or for the construction of dockwalls, walkways, plazas, parks, private
5roadways open to the public, or similar improvements, or for any other public
6infrastructure improvements, that are located entirely in that district, if the work
7on those improvements is subject to s. 66.0903 or is exempted from that section under
8s. 66.0903 (6).".
AB75-SSA1-CA1,79,9 9364. Page 706, line 22: after that line insert:
AB75-SSA1-CA1,79,16 10"(fm) "Minor service and maintenance work" means a publicly funded private
11construction project that is limited to minor crack filling, chip or slurry sealing, or
12other minor pavement patching, not including overlays, that has a projected life span
13of no longer than 5 years; the depositing of gravel on an existing gravel road applied
14solely to maintain the road; road shoulder maintenance; cleaning of drainage or
15sewer ditches or structures; or any other limited, minor work on private facilities or
16equipment that is routinely performed to prevent breakdown or deterioration.".
AB75-SSA1-CA1,79,18 18366. Page 707, line 1: after "demolition" insert ", or improvement".
AB75-SSA1-CA1,79,20 20368. Page 707, line 9: after "demolition" insert ", or improvement".
AB75-SSA1-CA1,79,21 21369. Page 707, line 16: delete lines 16 to 18.
AB75-SSA1-CA1,79,22 22370. Page 707, line 19: delete "unit." and substitute:
AB75-SSA1-CA1,80,6
1"(i) "Publicly funded private construction project" means a construction project
2in which the developer, investor, or owner of the project receives direct financial
3assistance from a local governmental unit for the erection, construction, repair,
4remodeling, demolition, or improvement, including any alteration, painting,
5decorating, or grading, of a private facility, including land, a building, or other
6infrastructure.".
AB75-SSA1-CA1,80,8 7371. Page 707, line 20: delete "that is subject to s 66.0903" and substitute ",
8as defined in s. 66.0903 (1) (h),".
AB75-SSA1-CA1,80,9 9372. Page 708, line 1: delete "facility" and substitute "residential property".
AB75-SSA1-CA1,80,10 10373. Page 708, line 2: after that line insert:
AB75-SSA1-CA1,80,16 11"(im) "Supply and installation contract" means a contract under which the
12material is installed by the supplier, the material is installed by means of simple
13fasteners or connectors such as screws or nuts and bolts and no other work is
14performed on the site of the publicly funded private construction project, and the
15total labor cost to install the material does not exceed 20 percent of the total cost of
16the contract.".